H-4 NAVSEA 5252.233-9103
DOCUMENTATION OF REQUESTS FOR EQUITABLE ADJUSTMENT (APR 1999)
(a) For the purposes of this special contract requirement,
the term "change" includes not only a change that is made pursuant to
a written order designated as a "change order" but also (1) an
engineering change proposed by the Government or by the Contractor and (2) any
act or omission to act on the part of the Government in respect of which a
request is made for equitable adjustment.
(b) Whenever the Contractor requests or proposes an
equitable adjustment of $100,000 or more per vessel in respect to a change made
pursuant to a written order designated as a "change order" or in
respect to a proposed engineering change and whenever the Contractor requests
an equitable adjustment in any amount in respect to any other act or omission
to act on the part of the Government, the proposal supporting such request
shall contain the following information for each individual item or element of
the request:
(1) A description (i) of the work
required by the contract before the change, which has been deleted by the
change, and (ii) of the work deleted by the change, which already has been
completed. The description is to include a list of components, equipment, and
other identifiable property involved. Also, the status of manufacture,
procurement, or installation of such property is to be indicated. Separate
description is to be furnished for design and production work. Items of raw
material, purchased parts, components and other identifiable hardware, which
are made excess by the change and which are not to be retained by the
Contractor, are to be listed for later disposition;
(2) Description of work necessary to undo work already
completed which has been deleted by the change;
(3) Description of work not required by the terms hereof
before the change, which is substituted or added by the change. A list of
components and equipment (not bulk materials or items) involved should be
included. Separate descriptions are to be furnished for design work and production
work;
(4) Description of interference and inefficiencies in
performing the change;
(5) Description of each element of disruption and exactly
how work has been, or will be disrupted:
·
The calendar period of time during which
disruption occurred, or will occur;
·
(ii) Area(s) aboard the vessel where disruption
occurred, or will occur;
·
(iii) Trade(s) disrupted, with a breakdown of
man-hours for each trade;
·
(iv) Scheduling of trades before, during, and
after period of disruption;
·
(v) Description of measures taken to lessen the
disruptive effect of the change;
(6) Delay in delivery attributable solely to the change;
(7) Other work attributable to the change;
(8) Supplementing the foregoing, a narrative statement of
the direct "causal" relationship between any alleged Government act
or omission and the claimed consequences therefore, cross-referenced to the
detailed information provided as required above; and
(9) A statement setting forth a comparative enumeration of
the amounts "budgeted" for the cost elements, including the material
costs, labor hours and pertinent indirect costs, estimated by the Contractor in
preparing its initial and ultimate proposal(s) for this contract, and the
amounts claimed to have been incurred and/or projected to be incurred corresponding
to each such "budgeted cost" elements.
(c) Each proposal in excess of $100,000 submitted in support
of a claim for equitable adjustment under any requirement of this contract
shall, in addition to the information required by paragraph (b) hereof, contain
such information as the Contracting Officer may require with respect to each
individual claim item.
(d) It is recognized that individual claims for equitable
adjustment may not include all of the factors listed in paragraph (b) above.
Accordingly, the Contractor is required to set forth in its proposal
information only with respect to those factors, which are comprehended, in the
individual claim for equitable adjustment. In any event, the information
furnished hereunder shall be in sufficient detail to permit the Contracting
Officer to cross-reference the claimed increased costs, or delay in delivery,
or both, as appropriate, submitted pursuant to paragraph (c) of this
requirement, with the information submitted pursuant to paragraph (b) hereof.